(a) Gross profit recognized in: 2004 2005 2006 Contract price $1,500,000 $1,500,000 $1,500,000 Costs: Costs to date $400,000 $935,000 $1,070,000 Estimated costs to complete 600,000 1,000,000 165,000 1,100,000 0 1,070,000 Total estimated profit 500,000 400,000 430,000 Percentage completed to date 40%* 85%** 100% Total gross profit recognized 200,000 340,000 430,000 Less: Gross profit recognized in previous years ...